The construction project for a drainage system aimed at preventing flooding

Division 
Construction Management (CM)

Project Owner/ Client 
-
Job Types
Use of Building Information Modeling (BIM) to control the construction work

Location
the Pa Mok community area, Ang Thong Province

Value of Work
-
Last Year Completed
2023
 
The construction project for a drainage system aimed at preventing flooding in the Pa Mok community area, Ang Thong Province. The project is divided into four phases:

Phase 1: Length 1,178.60 meters, located in the administrative area of Tambon Bang Sedet.
Phase 2: Length 1,678.30 meters, located in the administrative area of Tambon Bang Sedet.
Phase 3: Length 1,243.00 meters, located in the administrative area of Tambon Bang Sedet.
Phase 4: Length 1,267.70 meters, located in the municipal area of Tambon Pa Mok.

The total project length is 5,367.60 meters. The text mentions the use of Building Information Modeling (BIM) to control the construction work, starting with creating a 3D model based on the contract, allowing those overseeing the project to visualize progress in a 3D format.

Project Details:
Department/Division: Construction Management (CM)
Project Location: Tambon Pa Mok, Pa Mok District, Ang Thong Province, under the administration of Tambon Bang Sedet, Pa Mok District, Ang Thong Province.
Duration: 900 days.
Project Owner/Contractor: Department of Public Works and Town Planning.

Youtube https://youtu.be/Xtf1cA2u6vY