Instrumented Static Pile Load Test: The bridge across the Chao Phraya River
Division หน่วยธุรกิจทดสอบเสาเข็ม (Pile Testing Business Unit)
Project Owner/ Client Italian-Thai Development PCL Job Types ทดสอบ Instrumented Static Pile Load Test Location The Kiakkai Bridge project, The bridge across the Chao Phraya River [Phase 2] Value of Work - Last Year Completed 2022
Testing: Instrumented Static Pile Load Test by STS Corp: PT-BU [STS Group] Project : The Kiakkai Bridge, The bridge across the Chao Phraya River [Phase 2] Pile Testing: Bored Pile Dia.1.80x65.00m. Reaction System : 4 nos. of Anchor Pile System Max Test Load: 4,500 tons Main Contractor: Italian-Thai Development PCL Piling Contractor: Italthai Trevi Co.,Ltd. Pile Testing Company: STS Corporation